36 men can complete a piece of work in 18 days working 6 hours a day. In how many days will 27 men complete the same work working 8 hours a day?

36 men can complete a piece of work in 18 days working 6 hours a day. In how many days will 27 men complete the same work working 8 hours a day?
posted 4 years ago by srk80


0 comments

    © 2024 HashOut. All rights reserved.


    Log in to your account

    Sign up to continue